Danilo Teston, CCM, LEED AP
Summary of
Qualifications Mr. Teston is a construction manager/ engineer
specialist working on a broad range of aviation projects including major hub
airports i.e. San Francisco International Airport (SFO) with $475 million
program budget. He has more than 25 years of experience in design and
construction projects across a broad range of all disciplines in construction
project management, architectural design, and code enforcement, with a proven
track record of completing projects on-time and within budget to satisfy client
requirements. He has experience with Federal Aviation Administration (FAA),
and the Transportation Security Administration (TSA) rules and guidelines,
Occupational Safety and Health Administration (OSHA) compliance and
proceedings, building and environmental regulations and compliance methods. Mr.
Teston has experience with systems utilized for tracking and distributions of
RFIs and Submittals using BIM 360 field, SharePoint, Prolog and Primavera for
accurate information and disseminating timely responses. Proven
ability to effectively solve and communicate practical solutions to Design and
construction problems. He has in-depth knowledge of project delivery methods
(design-bid-build, design-build, CM Agency (CMA), CM at Risk (CMAR). Mr.
Teston is very knowledgeable in contracting relationships, contracting terms
between the contractor, designer, owner and other parties in various delivery
methods. He is detail oriented, familiar with the Microsoft Office Suite,
Adobe Acrobat, AutoCAD familiar with interpreting critical path schedules
(Primavera 6), and with a Primavera Contract Manager and Expedition.). Relevant Project /
Work Experience PG&E Humboldt Bay Plant Decommissioning,
Eureka, CA. On Site Project Control Scheduler Mr. Teston provided construction management agency (Design Build project
delivery) for the construction of $25 million the PG&E Humboldt Bay Plant
decommissioning. He updates the schedule regularly during project design and
construction development. Evaluates critical and near critical path activity
sequences. Assesses actual progress based on site inspections. Analyzes
progress reports against the schedule. Evaluates critical and near critical
path activity sequences. Determines reasonable schedule logic and constraints
based on discussion with task owners and/or teams. Boeing
Composite Manufacturing Salt Lake City Airport Facility, Utah. Field
Construction Manager. Mr. Teston provided
construction management agency (CMA project delivery) for the construction of
$60 million the Boeing 787 Dreamliner facility modification. He assists the
Construction Manager to build sets and stages within budgets, to deadlines,
and to meet standards set by designers. He reports to Construction Manager
and assists with tasks such as scheduling, cost estimation and cost control.
He monitored construction to ensure that projects were built to the standards
of safety/ quality and are completed on schedule and within budget. He
Tracked RFI’s and Submittals status and ensure compliance of work in the
field using BIM 360 remotely access of documents (RFI, Submittals, Drawings,
Specifications) thru iPod or phone. He implements strong organizational
methods, close attention to detail and displays the ability to work under
pressure. Additionally, he oversees various construction plans and procedures
such as: Construction Assurance Plan, Safety Program, Hazard Analysis,
Construction Integration Testing and Acceptance Plan. San
Francisco International Airport (SFO), California. Construction Engineer Three Story Boarding Area
“A”. Mr. Teston
worked on the design and construction at San Francisco International Airport
(SFO), three story Boarding Area “A”, Secure Connector, Tunnels A, C and D,
and concession. A $475 million program using Construction Management at Risk
(CMAR) project delivery. He represented the owner and/or Architect in
all project meetings and other field matters relating to project construction
of the project. He made periodic site visits to the project, recorded
observations and reported to the Project Administrator all observations
related to completion status, quality of workmanship and compliance with the
Contract Documents. His responsibilities included the transmission of large
quantities of paper work and project documentation particularly AIA
standardized documents. He was responsible for the comprehensive and timely
administration of all project related documentation and information. He acted
as arbiter of the contract documents. He monitored the contractor performance
and progress, and periodically reported same to the Project Manager. He
ensures and oversees RFI and Submittals distribution, receiving and tracking
RFI and submittal responses according to program procedures. He scheduled, coordinated and conducted progress meetings. He prepared
change orders, monitored RFIs and submittals. He monitored closeout
submittals and performed periodic construction site visits. He reviewed all
submittals from the design sub-contractors, including Civil Engineer drawings
for conformance to standards and constructability. He is experienced in
interpreting contract drawings and specifications, assisting with resolutions
for technical engineering problems with the assigned discipline(s) and
coordinating application of the solutions. Phoenix Sky Harbor Airport (PHX), San Francisco
International Airport (SFO), Menita San Jose International Airport (SJC)
Federal Aviation Administration (FAA) for their Noise Abatement Program. Owner
Representative, QA/QC. Mr. Teston served as
Construction Manager Agency (CMA project delivery) and represented United
State Federal Aviation Administration (FAA) for their Noise Abatement $150
million Program. Responsible in Administering the Owners contract with the
Contractors, Design Professional and others related parties. Review and
evaluate deviation from schedule. Review and approve invoices and process
payment applications. Review and approve Construction contract Change Orders
and processing related documents. Monitor and tracked requests for
information (RFI), submittals, bulletins, as built drawings and close out
documentation.
Supervise other personnel at the construction
site. Communicate appropriately with regulatory agencies to ensure compliance
with relevant laws. Conducting periodic progress meeting. Manage the
communication process with the public and other as needed. Manage project
financing. Work closely with all responsible parties on the construction
project especially with the Clerks of the Works and Construction
Superintendent. responsible for quality assurance enforcement; project
coordination with various agencies, designers, and contractors; the
preparation of plans, specifications, and submittals; RFIs; scheduling
reviews; cost proposal and change order estimations, negotiations, and
approvals; safety enforcement; payment evaluations; and construction
documentation from start-up to close-out. Conducted projects construction
quality assurance to confirm all work and materials is in accordance with the
contract plans, specifications, and established standards of quality. A.B. Won
Pat International Airport Authority, Guam. Construction engineer. Mr. Teston provided construction engineering support for the
construction of terminal expansion Phase 1 project. The $710 million with
traditional Design Bid Build project completed phase featured an expanded
terminal space of 550,000 sq. ft. from 220,000 sq. ft., a new larger customs
and immigration hall, public parking lot with 710 spaces, new and expanded
retail space, an automated baggage system capable of processing 120 bags per
minute, and four pairs of moving walkways along the concourse. He was
responsible for the methods and solutions for complex engineering problems
and selects the most efficient and economical manner in meeting the
objectives. Applied advanced engineering techniques and analyses within a
discipline. Managed a subtask of a larger project or study in accordance with
contractual obligations. Responsible for the technical excellence of the
engineering functions of the project including coordination of technical disciplines,
procurement of materials and equipment, and construction planning assistance.
Review and payment recommendation of pay applications based on field
progress. Construction schedule monthly review. Review of change orders,
recommend issuance of field change orders; review documents for potential A/E
errors and omissions. U.S. Army
Military Housing Privatization, Alaska. Construction Manager. Mr. Teston managed Ft Wainwright and Ft Greely, US Army housing
privatization on-site field construction activities associated with the
completion of $55 million Design Build Mini IDP (Initial Development Period)
project with ongoing Full IP (Initial Development Period) worth $255 million.
Developed scope of work, supervised design from schematic design (SD-30%
documents), design development documents (DD-60% documents), construction
documents (CD-100% documents), bid and award, and construction of new and
renovation and fit-out military housing projects. Prepared construction
status and cost reports for presentation to the client. Liaison with other
departments required for completion of the project or impacted by the
construction. Reviewed and approved design documents and component estimates,
improved quality performance. Played a part in rebuilding the project team
with talented quality control managers, developed training and improved
morale or team work, resulting in improved client’s corporate image and
reputation, good quality homes for soldiers. Review and monitored Civil works
included route widening, truck climbing, wider roadway, and additional of
shoulders. Performed inspection work for drainage systems, asphalt paving,
grading or dirt work, traffic controls, SWPPP, and striping. At,
construction/rehabilitation of 50 miles neighborhood collector roads,
assigned as the Traffic Control Inspector. Bristol-Myers
Squibb, Large-Scale Cell Culture Manufacturing Facility, MA. Field Engineer. Mr. Teston provided construction management and commissioning,
qualification, and validation support services for Bristol-Myers Squibb’s
large-scale cell culture manufacturing facility in Devens, Massachusetts. A
Construction Management at Risk (CMAR project delivery method), $750 million
project. Responsible for quality assurance, quality control, and
project engineering for Pharmaceutical construction management and
commissioning, qualification, and validation support services for a
large-scale cell culture manufacturing facility. In (CQV) division, Created a
system to identify all pharmaceutical clean areas finishes and equipment for
installation. Introduced a schedule by coordinating with the Quality Control
and Assurance department to gather and bring us up to speed on Primavera
Construction Management to ensure all technical submittals, change orders,
RFI’s and shop drawings were approved. The operating efficiency was improved
by 20% because of the eliminated unnecessary procedures. QA/QC for the
construction of 5-mile stretch of arterial roads. Performed inspection for
grading, asphalt, concrete, pavement works, and traffic control/Construction
Zone Enhanced Enforcement Program (COZEEP). Duties included preparing ARE
Engineer’s Daily Report and Extra Work daily reports if needed; and preparing
quantity calculations for monthly estimates. Oakland
Unified School District, OUSD Modernization Program, Owner Representative. Mr. Teston handled various school projects for OUSD school
modernization namely, Bella Vista Elementary School, La Fayette Elementary
School, Piedmont Elementary School, Lakeview Elementary School. Responsibilities
include: preliminary estimate design fee proposal; issuing requests for
proposals to A/E firm(s); validating A/E fee proposals according to client
budget; and issuing NTP. Conducts site surveys with specialized consultants
prior to design to provide pertinent information to design team regarding
approach, including site soils investigation and lead and asbestos surveys of
a site or existing building from a logistical and feasibility standpoint.
Supervises all activities associated with assigned projects, including
control, organization, planning and design coordination with A/E firm and
communication with client. Responsible
for coordinating preliminary DSA meeting(s) and manages DSA approval. In
addition, verifies that all drawings issued by the A/E firm are completed,
accurate and comply with owner’s standards and specifications. Oversees
construction work on weekly meetings. Reviews all RFIs and submittal of
change order estimates for work outside of contracted scope (unforeseen
conditions) prior to commencing work. Reviews all change orders from all
construction projects with CMs and assesses their impact on the District then
helps OARs/AOR for processing FCD/CCD through DSA processing. Prepared specification, and verified that all drawings and specifications
issued for DSA and Bid package(s) were completed and accurate per owner’s
standards and specifications. Coordinated RFPs from company associates and
conducted project turn over meetings with Design coordinator and Key
associates. Oversaw construction work and weekly meeting(s); response to all RFIs,
and submittal of change order estimates for work outside of contracted scope
(unseen condition(s)) prior to commencing work. 1 |
|
|
||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|